Floor bounce

twocals
twocals Forum Participant Posts: 117 ✭✭
edited October 2019 in Caravans #1

After a few days of proper difficult decisions regarding drilling floors filling with one shot green ,we did it ,no more bounce solid as a rock. Phew.

Comments

  • lornalou1
    lornalou1 Forum Participant Posts: 2,169
    1000 Comments
    edited October 2019 #2

    Looks perfect. Ever thought of doing this as a career.

  • twocals
    twocals Forum Participant Posts: 117 ✭✭
    edited October 2019 #3

    Thanks for that lornalou, we are pretty pleased with the result and no, my  knees still hurt.🤪

  • oneeasygeezer
    oneeasygeezer Forum Participant Posts: 4
    edited October 2019 #4

    Hi I've got the same problem with the floor of my Lunar Delta I've been quoted £600-£750 for doing just the central walkway! I'd appreciate it if you could tell me how you went about it, i.e. what did you use, what spacing / pattern did you come up with, what depth did you drill to ensure all gaps were filled?  

  • EasyT
    EasyT Forum Participant Posts: 16,194
    1000 Comments
    edited October 2019 #5

    It is a shame that this site does not have a private message facility as I am sure that Twocals would happily supply info.

  • twocals
    twocals Forum Participant Posts: 117 ✭✭
    edited October 2019 #6

    Hi, we were phased out by prices. It cost us £30. Cut vinyl flooring out following pattern of the area you need repairing then drill 8mm holes to a depth of 30 mm 4 inches apart make sure the depth takes you to the bottom wood panel and not through it, cover each hole with masking tape and pierce, this stops the green escaping onto your floor. We filled with green 2525 epoxy resin bought from local caravan shop £15.you will also need 8x30 mm dowels to bung each hole.gently pour green in until nearly flush with the floor.keep pressing the floor to disperse and top up, do not over fill ,once all dowels are in you have to weigh the floor down we used 4 x 12 packs of water. Leave for 48hrs remove masking tape sand excess green and dowel to make smooth.vinyl put back with double sided carpet tape. 5 days away last week solid as a rock.hope this helps.

  • EasyT
    EasyT Forum Participant Posts: 16,194
    1000 Comments
    edited October 2019 #7

    Glad that you were still viewing Twocals

     
  • twocals
    twocals Forum Participant Posts: 117 ✭✭
    edited October 2019 #8

    Thanks EasyT, Yeah usual daily look ,totally agree with private message but glad to help anyone.

  • oneeasygeezer
    oneeasygeezer Forum Participant Posts: 4
    edited December 2019 #9

    Thanks for the update twocals, sorry for the delay in responding but I've been away. This will be my first job after the Christmas break. 

     

     

  • ocsid
    ocsid Forum Participant Posts: 1,395
    1000 Comments
    edited December 2019 #10

    Thanks "twocals".

    Not that I need it, but still wishing to better understand the technique.

    Am I right in reading as the holes and dowels are both 30mm deep, the final structural arrangement leaves the floor effectively on a multitude of dowel strut piles?

    ie the compressive loads now are no longer solely via the foam core, but primarily the dowels from the top to bottom ply skins?

    Should that be the principle, I can see it might be wise in initially determining the depth others need to drill their floors, then almost finger screwing the drill bit whilst going through the soft foam so as to "find" the opposing ply wood without puncturing it.

  • cyberyacht
    cyberyacht Forum Participant Posts: 10,218
    1000 Comments
    edited December 2019 #11

    If the holes are filled with resin, tapping dowels in the full depth must create a fair bit of hydraulic pressure that has to go somewhere. Is this to force the resin to expand through the surrounding foam?

  • ocsid
    ocsid Forum Participant Posts: 1,395
    1000 Comments
    edited December 2019 #12

    Hopefully into the fractures in the foam and or its bond to the ply, that necessitated the job being needed?

  • twocals
    twocals Forum Participant Posts: 117 ✭✭
    edited December 2019 #13

    Hi, all just noticed this start again. Yes i drilled the floor then hand screwed the drill bit through the foam till i hit wood. I seem to remember it was about 33 mil ,the foam was very broken and powdery in places.the bungs were very easy to push in and like cy says i guess it spreads to all places as it expands.the bungs also stop the resiin escaping as well as offering rigidity to the foor.